Contract E8

It covers Ayias Fylaxeos parish area north of the motorway and Ekali area.

Contract E9

It covers “Panthea” area in the Mesa Geitonia municipality south of the new cemetery and up to the motorway, Ayios Athanasios municipality, Panioti area in Germasogeia municipality and the centres of the Communities of Palodia, Moutayiaka, Ayios Tichonas, Pyrgos and Parekklisia.

Contract E10 

This contract includes the construction of the new pumping station Z and the construction of a second main collector connecting PSD with PSZ. The construction of pumping station M was cancelled. 

Contract E11

This contract shall include the upgrading of the existing six pumping stations. It shall also include the installation of the SCADA system. Major expansion works are particularly expected at pumping station E.

Contract E12

This contract has been signed in September 2012 and includes the new twin force main collector that shall be constructed along the existing force main collector from Pumping Station F to the Moni WWTP of about 4 km length. The pipe laying contract shall cost about €3 million, whereas the pipe supply an additional amount of €3.5 million.

Contract E13

The results of the 2009 Master Plan Update, have shown that a new WWTP constructed in the West would better serve the West SBLA Area and would also improve the overall reliability of the system. This contract shall include the construction of a new wastewater treatment plant in the West part of Limassol of an estimated capacity of 15.000 m3/day with a significant part of the flow from the northern and western part of the system being diverted to it, thus relieving the coastal main collector and the existing eastern WWTP. 

Tenders are expected to be invited by the end of 2010 and it is expected that the contract will be signed by mid 2011.

Contract E14

This contract provides for the rehabilitation of the coastal main collector, consisting of gravity mains and force mains.

 

 