Short description of the areas to be covered by the remaining contracts:

Contract E1

The area within the bounds of the Lemesos Municipality that is surrounded by Makarios avenue, Spyros Kyprianou avenue, Ayias Fylaxeos street and Garillis river, including the area around Nikou Pattichi street.

This Contract with a contract value of €14.293.267 has been signed in June 2008 and construction works began in September 2008. These works have been completed in September 2010.

In addition to the sewerage works, the construction of the storm water drainage works has been completed in the area of “Panayidis Foundation” and around the church of Ayia Varvara at Zakaki, which often suffers from serious flooding incidents due to the huge flow of storm water from the north suburbs. In addition, the storm water drainage works along Vasileos Konstandinou street has been constructed in the critical area south of “Tsirion” Stadium.

Contract E2

This contract with a contract value of €14.832.600 has already been signed and construction works began in March 2009. The expected completion date is June 2011.

The contract area includes the centre of the Ayios Athanasios Municipality, Kato Polemidia Municipality and the Ayia Fyla area east of “Ekali” and north of the Lemesos-Lefkosia bypass road.

Contract E3

This contract with a contract value of €15.768.001 has been completed in September 2009, approximately six months ahead of the contract date.

It covers the area that includes part of Zakaki, Ayios Ioannis and Omonoia and is surrounded by Garillis river, Spiros Kyprianou avenue, Pafos road, Miltonos, Serifou, Agaristis and Sarantoporou streets, Omonoia avenue and the Makarios avenue.

Contract E4

This contract with a contract value of €12.846.297 has also been signed and construction works have started and the expected completion date is February 2012.

It covers the area that includes the remaining of Zakaki area west of Miltonos street and up to the new link road leading to the Port. It also covers part of Kato Polemidia Municipality north of the First Industrial Area of Limassol and south of Pafos road.

Contract E5

This contract with a contract value of €9.923.000 was awarded early 2010 and construction works have started in June 2010.

It covers the area surrounded by Spiros Kyprianou avenue, the motorway, the Ayios Athanasios avenue and the Petrou Tsirou/Georgiou Papandreou streets, and the expected completion date is April 2012.

Contract E6

It covers the area surrounded by Spiros Kyprianou avenue, the motorway and west of the Petrou Tsirou and Georgiou Papandreou streets. This contract consists of substantial storm water drainage works and the total contract value is expected to exceed €25 million. 

Contract E7

It covers the area surrounded by Spiros Kyprianou avenue, the motorway and west of the Marinou Geroulanou street. The area within the bounds of the Kato Polemidia Municipality east and south of the New Limassol General Hospital. The Government (self-housing) estate and the surrounding built-up areas in the Pano Polemidia Community.

 

 